Skip to main content
Skip table of contents

When Line Level Unit is Defined for a Line

(V 02.00.01-00)

The Pricing and Billing for an Order will differ in different scenarios when Unit is defined for the line. The section below explains different scenarios"

Scenario 1

In an Order, when Line Level Unit is set Day and Item Price is Defined, the functionality will be as below:

System will consider the DIW and DIM which is applicable for the line.

The Illustration below explains how Order line amount is calculated for each Day.

Illustration 1:

  1. Define Invrental Price as below:

    1. Day Price = 40

    2. Week Price = 60

    3. Month Price = 100

  1. Set the Unit as Day

  2. DIW as 3 and DIM as 9

Pricing

Table 1.0

Day

Order Line Amount

Calculation

1

40

Day Price of 40 will be applied for Day 1

2

80

40*2 = 80

3

120

40*3 = 120

4

120

Day 4 to 7 Price will remain as 120, as DIW is 3.

5

120

6

120

7

120

8

160

Price on 1st Day of 2nd week :

= Price of 1st week  + Price for 1st Day in 2nd Week

= 120+40 = 160

9

200

Similarly for Price 2nd Day of 2nd Week :

= 120+80 = 200

10

240

Price for 3rd Day of 2nd Week is:

= 120+120 = 240

11

240

Price for the next 4 days of the 2nd week i.e., 11th day to 14th day will remain as 240, since DIW is only 3.

12

240

13

240

14

240

15

280

Price on 1st Day of 3rd week

= Price of 1st week  + Price 2nd Week  + Price of 1s day of 3rd week

= 120 + 120 + 40 = 280

16

320

Similarly for Price 2nd Day of 3rd Week

= 240+80 = 320

17

360

Price 3rd Day of 3rd Week

= 240+120 = 360

18

360

Day 18 to 28 the Price will remain as 360, since only 9 days in a month has to be charged as DIM = 9

 

19

360

20

360

21

360

22

360

23

360

24

360

25

360

26

360

27

360

28

360

29

400

Price for 1 month + 1 Day

= 360 + 40 = 400

  • From the 29th Day the Pricing will again go in a Loop and Loop back to Day 1.

Billing

Billing for an Order will be different when Pricing Month By is set to 28 Days or Calendar Month, the section below explains the different cases:

  • When Pricing Month By is 28 Days and Billing Terms is Monthly:

  • For an Order having duration of 1month starting from 1st JUNE:

Order Details will be as follows:

Order Duration = 31 Days and Amount = 480

Table 2.0 Invoice Details

Invoice #

From Date

To Date

Amount

INV#1

01-06-2010

28-06-2010

360

INV#2

29-06-2010   

01-06-2010

120

  • When Pricing Month By is set as Calendar Month and Billing Terms is Monthly:

Note: When Pricing Month By is set to Calendar Month, then system will always consider the Monthly Price for Pricing and Billing.

  • For an Order having duration of 1month starting from 1st JUNE:

Order Details will be as follows:

Order Duration = 31 Days and Amount = 400

Table 2.1 Invoice Details

Invoice #

From Date

To Date

Amount

INV#1

01-06-2010

30-06-2010

360

INV#2

01-07-2010   

01-07-2010

40

Note:  When Billing Terms is changed, system will retain the Invoices which are already generated with the old billing terms and the changed Billing Terms will be applied for the other days for which Invoice is not generated

Scenario 2

In an Order, when Line Level Unit is set Week and Item Price is defined, the functionality will be as below:

  • System will consider the DIW and DIM which is applicable for the line

  • Order line price will be considered based on Weekly Price.

The illustration below explains how Order line amount is calculated for each Day

Illustration 2:

  1. Define Interval Price as below:

    1. Day Price = 40

    2. Week Price = 60

    3. Month Price = 100

  2. Set the Unit as Week

  3. DIW as 3 and DIM as 9

Pricing

Table 3.0

Day

Order Line Amount

Calculation

1

20

Price of Day 1 is:

Weekly Price / DIW * Duration

= 60/3*1=20

2

40

Price of Day 2 is:

Weekly Price / DIW * Duration

= 60/3*2=40

3

60

Price of Day3 is:

Weekly Price / DIW * Duration

= 60/3*3=60

4

60

Price from Day 4  to Day 7 will remain as 60, since DIW should not exceed 3

5

60

6

60

7

60

8

80

Price of 1st Day of 2nd week  is:

1st Week Price + [Weekly Price / DIW * Duration]

= 60 + [60/3*1] =80

9

100

Price of 2nd Day of 2nd week  is:

1st Week Price + [Weekly Price / DIW * Duration]

= 60 + [60/3*2] =100

10

120

Price of 3rd Day of 2nd week  is:

1st Week Price + [Weekly Price / DIW * Duration]

= 60 + [60/3*3] =120

11

120

Price from Day 11  to Day 14will remain as 120, as Price for 2 weeks cannot exceed 120 since DIW should not exceed 3

12

120

13

120

14

120

15

140

Price of 1st Day of 3rd week  is:

[Price of 1st week + Price  2nd week] + [Weekly Price / DIW * Duration]

= [60 + 60] + [60/3*1] =140

16

160

Price of 2nd Day of 2nd week  is:

[Price of 1st week + Price  2nd week] + [Weekly Price / DIW * Duration]

= [60 +60] + [60/3*2] =160

17

180

Price of 3rd Day of 2nd week  is:

[Price of 1st week + Price  2nd week] + [Weekly Price / DIW * Duration]

=[ 60 + 60] + [60/3*3] =180

18

180

Price from Day 18 to Day 28 will remain as 180, as DIM is only 9 and cannot exceed the same

19

180

20

180

21

180

22

180

23

180

24

180

25

180

26

180

27

180

28

180

29

200

 

Billing

Billing for an Order will be different when Pricing Month By is set to 28 Days or Calendar Month, the section below explains the different cases:

  • When Pricing Month By is 28 Days and Billing Terms is Monthly:

  • For an Order having duration of 1month starting from 1st JUNE:

Order Details will be as follows:

Order Duration = 31 Days and Amount = 240

Table 4.0 Invoice Details

Invoice #

From Date

To Date

Amount

INV#1

01-06-2010

28-06-2010

180

INV#2

29-06-2010   

01-06-2010

60

  • When Pricing Month By is set as Calendar Month and Billing Terms is Monthly:

Note: When Pricing Month By is set to Calendar Month, then system will always consider the Monthly Price for Pricing and Billing.

  • For an Order having duration of 1month starting from 1st JUNE:

Order Details will be as follows:

Order Duration = 31 Days and Amount = 200

Table 4.1 Invoice Details

Invoice #

From Date

To Date

Amount

INV#1

01-06-2010

30-06-2010

180

INV#2

01-07-2010   

01-07-2010

20

Note:  When Billing Terms is changed, system will retain the Invoices which are already generated with the old billing terms and the changed Billing Terms will be applied for the other days for which Invoice is not generated

Scenario 3

In an Order, when Line Level Unit is set, Week, Week Price is blank but Day and Month Price is defined then the functionality will be as below:

  • Day Price will be considered for calculation of Weekly Price.

  • System will consider the DIW and DIM which is applicable for the line.

The Illustration below explains how Order line amount is calculated for each Day.

Illustration 3

  1. Define Interval Price as below:

    1. Day Price = 40

    2. Week Price = Blank

    3. Month Price = 100

  2. Set the Unit as Week

  3. DIW as 3 and DIM as 9

Pricing

Table 5.0

Day

Order Line Amount

Calculation

1

40

Price for Day 1 is 40

2

80

Price of Day 2  =

Day Price * Duration

= 40*2 =80

3

120

Price of Day 3  =

Day Price * Duration

= 40*3 =120

4

120

Price from Day 4 to Day 7 will remain  120, as DIW is only 3 and it cannot exceed 3

5

120

6

120

7

120

8

160

Price of 1st Day of 2nd week  is:

1st Week Price + [Day Price * Duration]

= 120 + [40*1] =160

9

200

Price of 2nd Day of 2nd week  is:

1st Week Price + [Day Price * Duration]

= 120 + [40*2] =200

10

240

Price of 3rd Day of 2nd week  is:

1st Week Price + [Day Price * Duration]

= 120 + [40*3] =240

11

240

Price from Day 11 to Day 14 will remain  240, as DIW is only 3 and it cannot exceed 3

12

240

13

240

14

240

15

280

Price of 1st Day of 3rd week  is:

[Price of 1st week + Price  2nd week] + [Day Price * Duration]

= [120 + 120] + [40*1] =280

16

320

Price of 2nd Day of 3rd week  is:

[Price of 1st week + Price  2nd week] + [Day Price * Duration]

= [120 + 120]  + [40*2] =320

17

360

Price of 3rd Day of 3rd week  is:

 [Price of 1st week + Price  2nd week] + [Day Price * Duration]

= [120 + 120]  + [40*3] =360

18

360

Price from Day 18 to Day 28 will remain as 360, since DIM is 9 and should not exceed 9

19

360

20

360

21

360

22

360

23

360

24

360

25

360

26

360

27

360

28

360

Billing

Billing for an Order will be different when Pricing Month By is set to 28 Days or Calendar Month, the section below explains the different cases:

  • When Pricing Month By is 28 Days and Billing Terms is Monthly:

  • For an Order having duration of 1month starting from 1st JUNE:

Order Details will be as follows:

Order Duration = 31 Days and Amount = 480

Table 6.0 Invoice Details

Invoice #

From Date

To Date

Amount

INV#1

01-06-2010

28-06-2010

360

INV#2

29-06-2010   

01-06-2010

120

  • When Pricing Month By is set as Calendar Month and Billing Terms is Monthly:

Note: When Pricing Month By is set to Calendar Month, then system will always consider the Monthly Price for Pricing and Billing.

  • For an Order having duration of 1month starting from 1st JUNE:

Order Details will be as follows:

Order Duration = 31 Days and Amount = 400

Table 6.1 Invoice Details

Invoice #

From Date

To Date

Amount

INV#1

01-06-2010

30-06-2010

360

INV#2

01-07-2010   

01-07-2010

40

Note:  When Billing Terms is changed, system will retain the Invoices which are already generated with the old billing terms and the changed Billing Terms will be applied for the other days for which Invoice is not generated

Click here to view the Details and Illustration when Unit is Blank

Click here for information on Auto Extending Duration on Posting Invoice

JavaScript errors detected

Please note, these errors can depend on your browser setup.

If this problem persists, please contact our support.